We just posted a nice update to our TeamDirection Project 2007-- just in time for Christmas (I think it'll make a *great* stocking stuffer :).

We fixed over 40 bugs of varying severity, and included a couple feature requests. Bugzilla is our bug tracker of choice, and here's the delta:


2190

nor

P3

Wind

VERI

FIXE

It is only possible to insert tasks above from the right ...

2092

nor

P3

Wind

VERI

FIXE

Unsharing and sharing a project to the same SP site will ...

2108

nor

P3

Wind

VERI

FIXE

Tasks with IW don't get pushed out far enough when linking

2114

nor

P3

Wind

VERI

FIXE

IW causes backward links when removed

2551

nor

P2

Wind

VERI

FIXE

Thing2 should update task durations for MindManager

2579

nor

P2

Wind

VERI

FIXE

Exporting with MM closed will still export the project

2580

nor

P2

Wind

VERI

FIXE

Wrong message when trying to export the project with no M...

2600

nor

P2

Wind

VERI

FIXE

MS Project export doesn't close wizard when done

2609

nor

P2

Wind

VERI

FIXE

Trying to notify members from Share Wizard with no Outloo...

2614

nor

P2

Wind

VERI

FIXE

3.1 project with no resources or links fail to import

2615

nor

P2

Wind

VERI

FIXE

Implement 'Publish Summary Task' option

2564

nor

P2

Wind

VERI

FIXE

Sharing on SP site with members will always ask to 'Map c...

2566

nor

P2

Wind

VERI

FIXE

Release version appears expired after upgrading from Beta...

2575

nor

P2

Wind

VERI

FIXE

If breaking link with MS Project or MM file, project stay...

2578

nor

P2

Wind

VERI

FIXE

Tab Control needs to update Go To Task when swi...

2581

nor

P2

Wind

VERI

FIXE

There is no "open task list" option in Member Pane in Plu...

2587

nor

P2

Wind

VERI

FIXE

'Copy Task' should probably be enabled for projects in lo...

2591

nor

P2

Wind

VERI

FIXE

'I want to buy a license' in activation dialog should ope...

2597

nor

P2

Wind

VERI

FIXE

Undo doesn't work in any Linked mode

2598

nor

P2

Wind

VERI

FIXE

Cannot edit Date2 field from task information dialog whil...

2603

nor

P2

Wind

VERI

FIXE

Arrows keys in Project Save dialog are backward

2606

nor

P2

Wind

VERI

FIXE

'Go to task ..' counting tasks wrong in projects with sum...

2608

nor

P2

Wind

VERI

FIXE

Need to hide Map Tab in Resource management dialog window

2618

nor

P2

Wind

VERI

FIXE

Custom Resources that contains only numbers are align to ...

2619

nor

P2

Wind

VERI

FIXE

Able to select several resources in Reassign tab

2620

nor

P2

Wind

VERI

FIXE

Trying to reassign Me when there is no other members caus...

2623

nor

P2

Wind

VERI

FIXE

In Members list project creator appears with Groove bubbl...

2626

nor

P2

Wind

VERI

FIXE

Trying to click 'Go to task' for the summary task giving ...

1437

nor

P2

Wind

VERI

FIXE

'Schedule a meeting' option is available when no Outlook ...

2542

nor

P2

Wind

VERI

FIXE

Updating marks unchanged project as unread

2612

nor

P2

Wind

VERI

FIXE

Can't open project linked to a MS project with an excepti...

2617

nor

P2

Wind

VERI

FIXE

Publish Summary task check box in SW doesn't work

2625

nor

P2

Wind

VERI

FIXE

Workspace members stays in members list after unsharing

2582

nor

P2

Wind

VERI

FIXE

Projects can be dragged/dropped onto Search folders.

2583

nor

P2

Wind

VERI

FIXE

App does not recover from deleted project

2593

nor

P2

Wind

VERI

FIXE

Yes in 'Want to activate?' dialog when 1 day left doesn't...

2594

nor

P1

Wind

VERI

FIXE

Able to work with Plus edition after activating standard ...

2599

nor

P2

Wind

VERI

FIXE

Error occurs when updating dirty linked MS Project file

2602

nor

P2

Wind

VERI

FIXE

Task dependencies not getting exported to MS Project

2613

nor

P2

Wind

VERI

FIXE

Help>About for Plus does not say Plus


Phew, that was a lot of work! I hope you enjoy it and have a great holiday.